MARCH 2026UPDATE
Groundbreaking Ceremony Held
The groundbreaking ceremony was held on March 1, officially marking the start of the renovation.
Construction is scheduled to be completed by July, followed by interior preparations and final adjustments. The project is currently on track for a pre-opening in November 2026.
SEPTEMBER 2025UPDATE
Local Support Fund Established
Following a co-owner vote, the establishment of a local support fund was approved. The fund is intended to support community and environmental improvement initiatives in the surrounding area.
JUNE 2025UPDATE
Government Grant Approved
A government grant was approved to support the renovation of the property. The funds will be used specifically toward renovation-related works
MAY 2025UPDATE
Co-owner Site Visit & Community Engagement in Wakayama
Co-owners from around the world joined a three-day, two-night visit to the property and local community, engaging with residents and taking part in cultural and hands-on experiences. Key reflections were later shared with the wider co-owner group.
FEBRUARY 2025UPDATE
Architect Selected Through On-site & Online Proposal Session
The architect has been selected in collaboration with shareholders and local community members, through both on-site and online proposal sessions.
We held proposal sessions both on-site and online, inviting architects to share their ideas for the project. After reviewing the proposals together with shareholders and local community members, we selected the architect we will work with for the renovation.

NOVEMBER 2024UPDATE
Architect Application Opened
The application process for selecting an architect has been launched.
https://ryogonji.studio.site/
SEPTEMBER 2024UPDATE
Government Grant Application Approved by Co-owner Vote
Following a co-owner vote, it was decided to apply for the Nohaku government grant through the Ohtagawa Ryuiki Kyogikai (太田川流域協議会). The grant is expected to cover approximately half of the renovation and architectural costs, although it will result in a revised renovation schedule.
AUGUST 2024UPDATE
Fundraising Completed & Share Allocation Finalized
Fundraising for PlanetDAO001 was successfully completed, and shares were officially allocated to co-owners on August 8.
JANUARY 2027MILESTONE
Grand Opening
The property is scheduled to officially open in January 2027.
Following the pre-opening phase, we will welcome travelers and begin full operations, marking the completion of the project’s initial development phase.